Saturday, 7th of July 2012 The stain glasses of the main church hall's north wall have been installed. The main hall doors as seen in the photo's are being lifted and fitted with new door arches. It has also been decided to Lift the church floor by 14 inches instead of 7 inches as the Galle Road in front of the church is scheduled for another carpeting of 4 inches in the near future.
The Facade is reaching its final stages as the peek top of the triangle is being completed. Also seen in the photo's is the inner cone of the bell towers peek top which is to lifted up to the bell tower.
Work on puffing the corridor walls and pillars are progressing smoothly as well.