Sunday, 15th of July 2012 The Altar fence has been removed to facilitate the lifting of the altar as well as the church floor by 14 inches. The corridors are already been lifted. The main church hall and side wings will be lifted approximately 3 inches more than the corridors. Also doors are being made on the side wings so that the over flowing devotees may witness the mass from outside the church. Rewiring of the church is also proceeding smoothly. There are over 53 workers currently at work on the church, facade and mission house.
A set of devotees teamed up to assist the work of the church. They have started to remove the concrete tiles that cover the outer garden before the landscaping project buries them.